DAMP-PROOFING FLOORS
Apply by brush, a minimum of 2 coats, each at 0.8 litre per m2, carrying the treatment up the walls to join the existing wall DPC. Allow the first coat to dry before applying the second coat at right angles to the first. When dry, a sand/cement or concrete screed of approximately 50mm thick is then laid over the EVERBUILD® BLACK JACK® 908 D.P.M. membrane.
WATERPROOFING WALLS
If a condition of rising damp exists, the best form of treatment is the insertion of a damp proof course. Where dampness is due to penetration of the wall, proceed as follows:
a/ Exterior walls:
Level uneven surfaces with cement mortar. Apply three coats of EVERBUILD® BLACK JACK® 908 D.P.M. with a soft bristle brush, each at a rate of 0.5 ltr/m2, allowing each coat to dry before applying the next. Allow the final coat to become tacky, then blind with clean, sharp sand.
b/ Interior walls. (moderately damp)
Remove wallpaper, loose emulsion/gloss paint and any dust or grease. Make good any damaged or perished plaster. Lightly dampen the prepared surface and apply 3 coats of EVERBUILD® BLACK JACK® 908 D.P.M. with a soft bristle brush, each at a rate of 0.5 ltr/m2, allowing each coat to dry before applying the next. A horizontal strip running 300mm deep should be left uncoated at the top running the whole length of the wall. This permits trapped moisture to escape by evaporation.
c/ Interior walls (very damp)
Wherever possible, very damp walls should receive an external treatment such as waterproof render/masonry paint etc. If this is not possible, the following procedure may benefit - although it must be emphasised that only adequate external treatment will cure the most severe conditions.
Hack away old plaster from the entire area. Damage to joints or brickwork must be made good with cement mortar. When the mortar has dried, apply 3 coats of EVERBUILD® BLACK JACK® 908 D.P.M. with a soft bristle brush, each at a rate of 0.5 ltr/m2, allowing each coat to dry before applying the next. When the final coat has thoroughly dried, the wall should be re-plastered.
DECORATING
Gloss paints and other oil or alkyd based paints must not be used over a surface treated with EVERBUILD® BLACK JACK® 908 D.P.M.
Where EVERBUILD® BLACK JACK® 908 D.P.M. has been used over plaster, it is recommended that a lining paper, fixed with cellulose paste should be hung. This will provide a suitable surface for emulsion paints and for wallpapering.
NOTE: Vinyl coated papers or paper backed vinyls should NOT be hung over EVERBUILD® BLACK JACK® 908 D.P.M.
WATERPROOFING STRUCTURES
EVERBUILD® BLACK JACK® 908 D.P.M. will provide a waterproof membrane on bridge abutments, retaining walls, culverts, concrete or brick foundations. It also acts as a curing membrane when applied to green concrete.
The surface should be sound and free from dust, dirt and grease. Hot, very dry or absorbent surfaces should be dampened with water. Apply two coats of EVERBUILD® BLACK JACK® 908 D.P.M. each at a rate of 0.5 litre/m2.
FIXING WOOD BLOCKS AND MOSAICS
For fixing wood blocks of 12mm thickness and above, dip the bottom face of each block into the material and place into position immediately. Coverage is approximately 1.1 litre/m2.
For fixing wood mosaic panels, spread EVERBUILD® BLACK JACK® 908 D.P.M. onto the surface at 0.8 litres/m2 and place the panels into position immediately. A minimum of 24 hours should be allowed before sanding/trafficking.
Where under floor heating is incorporated into the sub floor the heating must be turned off for at least 48 hours before, and until after, tiling.
NOTE: On low porosity or non-porous surfaces, allow EVERBUILD® BLACK JACK® 908 D.P.M. to partially dry before placing the wood mosaics/blocks into position. In most circumstances a period of 30-40mins will suffice, but do not allow to dry off completely.
Under no circumstances, should such floorings be laid on existing floor coverings.
PLASTER/RENDER BONDING/KEYING
When a “keyed” surface is required (plastering onto glazed tiles, gloss painted walls and bricks, or to bond sand/cement renders) apply two coats of EVERBUILD® BLACK JACK® 908 D.P.M. each at a minimum rate of 0.25 litres/m2. Allow the first coat to dry before applying the second, and blind the second coat with clean sharp, dry, sand. Allow at least 48 hours before plastering or rendering (at least 6mm thickness)
NOTE if gloss or alkyd paints are to be used as a decorative finish, the plaster over the EVERBUILD® BLACK JACK® 908 D.P.M. must be applied in two coats to give a minimum total thickness of 15mm.
FIXING INSULATION BOARD, EXPANDED POLYSTYRENE AND CORK SLABS.
Surfaces should be clean, level and free from dust or loose matter. A coat should be applied to the porous base and the insulation material placed whilst the EVERBUILD® BLACK JACK® 908 D.P.M. is still wet. If necessary, the boards should be supported until the EVERBUILD® BLACK JACK® 908 D.P.M. has set.